Water is a hot topic for so many in the data center ecosystem. The use of artificial intelligence is growing significantly. For hyperscale data centers, that means managing equipment that uses more computing power and generates more heat than older servers. In addition, many communities are resisting data center projects out of fear of how these facilities threaten the local water supply. 

Traditional cooling methods, such as cooling towers and evaporative walls, consume significant amounts of water per unit of heat rejected. As compute density increases, these water-intensive cooling methods will become untenable for all but those facilities in water-abundant locations.

Four major hyperscale data center operators - Microsoft, Google, Amazon, and Meta - have pledged to use less water directly (through less water-intensive cooling) and fund water-replenishment projects in other locations to become water-positive by 2030. These operators, and any others considering reducing water use, risk falling short of that promise.

The fix has to start with how data centers cool their servers. Closed-loop, waterless systems are a step in the right direction, yet often trade water savings for higher electricity use (and the hidden water footprint of electricity generation); and shift the water use problem to the community where the power is generated.

The more complete answer is a hybrid approach: closed-loop systems that use small, precisely timed bursts of evaporative cooling with reclaimed (non-drinking) water. This can actually deliver on water-positive promises, without shifting the burden onto the power grid or other communities.

The Water Problem

There is no such thing as a waterless data center. Water use is problematic largely in specific regions - 72% of new data centers built in 2022 are in just five water-stressed states. And, analysis of approximately 14,000 data centers worldwide found that one-third of those currently under construction may experience more water-scarcity days by 2050. Because of increased scrutiny of data center water use, owners and operators are now considering water as the fourth pillar in evaluating a site's suitability. 

Why Hyperscalers Can't Get There From Here

The data center industry has treated water use as a choice between efficiency and peak performance. The pitch of waterless cooling is something companies use to appease municipal governments, regulators, and community members. Yet the science means it isn't as easy to keep that promise.

Cooling towers are thermodynamically efficient and also incompatible with water-positive goals. Data centers cannot reduce consumptive water loss without changing the fundamental heat rejection mechanism. Closed-loop systems (air-cooled chillers, dry coolers) do not use water directly but incur a severe efficiency penalty under peak ambient conditions.

A cooling system's efficiency (coefficient of performance) can drop by nearly half on the hottest days - the days when you most need the cooling to work well are exactly the days it works worst.

Precise Adiabatic Pre-Cooling

Precise adiabatic pre-cooling is key to improving the performance of a waterless cooling system. By strategically adding a small amount of water, data centers use it only on the hottest days, at the air intake, to get most of the cooling benefit of a wet system with a small fraction of the water consumption.

When you spray a fine mist of water into the air entering a cooling system, the water evaporates and cools the air, pulling the temperature from the dry-bulb reading toward the wet-bulb number. The gap between these numbers is the amount of free cooling you can get this way. In Phoenix, that gap is huge - 25-40°F. In humid Northern Virginia, evaporation provides 10-20°F of cooling benefit at the hottest point of the day. That is without accounting for additional heat sources, such as hot exhaust air blowing back into the intake.

Benefits

  • Lowers Peak PUE. Average PUE is not a meaningful metric for designing the power and water infrastructure or for assessing stress during worst-day conditions. Peak PUE is directly tied to design-day parameters: the same extreme ambient conditions that degrade the coefficient of performance and cause external computational fluid dynamics analyses to fail also determine how much cooling infrastructure a facility truly needs.
  • Unstrands Capacity to Free Up Power. Improved heat rejection efficiency is not just about lower costs; it also means more power, already wired and ready to go.
  • Helps Solve Failing External CFD Analyses. Data center sites often have a problem that dry/closed-loop heat rejection systems can't handle: the hot air exiting the cooling equipment and the exhaust heat from on-site backup diesel generators can be drawn into the cooling system's intake: The system is trying to cool itself with air that's already hot. An adiabatic assist addresses these CFD challenges directly. Because air-cooled chillers typically derate above 105°F and often risk shutdowns above ~131°F, adiabatic assist is often the only approach suitable for addressing failing CFDs caused by hot-air recirculation and generator exhaust.

What Decision Makers Need to Know

Adiabatic use cases are far more geographically diverse than commonly believed. The technology is beneficial for any facility with a gap between the ambient temperature at the cooling equipment's intake location and the wet-bulb temperature - for example, in Virginia, Georgia, New Jersey, and Oregon. 

The ideal fit for adiabatic pre-cooling is new construction or retrofits where the existing system is already dry (air-cooled chillers and/or dry coolers). This technology is also compatible with hybrid facilities that use a mix of wet and dry cooling. In these cases, the technology can reduce or even eliminate the need to run the water-hungry cooling towers.

Time to Act

For the data center industry, water stewardship is a real constraint on business. Permit delays, regulatory pressure, and failing CFD analyses cost developers time and money. 

Start by auditing your existing closed-loop portfolio in thermally challenged, water-stressed markets. These will give you the highest return on investment. Then move with urgency on existing commitments. The window for new campuses to contribute meaningfully to water-positive targets by 2030 is closing fast, and decisions made in the next twelve to eighteen months will determine whether you can meet those goals with real operational performance, not simply offsets.